AXForum  
Вернуться   AXForum > Microsoft Dynamics AX > DAX Blogs
All
Забыли пароль?
Зарегистрироваться Правила Справка Пользователи Сообщения за день Поиск Все разделы прочитаны

 
 
Опции темы Поиск в этой теме Опции просмотра
Старый 25.09.2015, 19:14   #1  
Blog bot is offline
Blog bot
Участник
 
25,459 / 846 (79) +++++++
Регистрация: 28.10.2006
emeadaxsupport: How to install and set up integration with MS Project in AX 2012 R3 successfully the first time
Источник: http://blogs.msdn.com/b/axsupport/ar...irst-time.aspx
==============

Before you begin

Integration with MS Project is done as an Office add-in for Dynamics AX 2012.
When you install Office add-ins for Dynamics AX 2012 it will only install the add-ins for the Office products that are installed on the client. If you did not have MS Project installed the first time you installed the AX Office add-ins, then you have to uninstall the Office add-ins using the AX 2012 setup. Then install MS Project and reinstall the Office add-ins using AX 2012 setup.

Important
There is released a binary/kernel hotfix (KB 3000048) for Dynamics AX 2012 R3 that fixes a problem with date format causing the sync to fail if you use other regional settings/date format than US format (selecting non US format in Control panel/Region).

The hotfix (KB 3000048) can be downloaded from LCS:
https://fix.lcs.dynamics.com/Issue/R...ce1e83ead57375

The AX kernel version for KB 3000048 is 6.3.164.3179 so if you are running with a kernel with higher build number, then you already have the fix.

Note:
When you install the AX Office add-ins then be sure that the KB 3000048 kernel or kernel hotfix with higher build number is slipstreamed with the AX Setup files.
https://technet.microsoft.com/en-us/.../hh378076.aspx



Installation

When you are ready to install, then this is a god guide to follow when installing MS Project integration:
http://blogs.msdn.com/b/axsa/archive...x-2012-r3.aspx



Setup after installation

Check that the services for project integration, AifProject and AifProjWBS, is deployed and Activated.
System administration > Services and Application Integration Framework > Inbound ports



If not activated, then Activate them by select the port and click Activate button.
If not deployed, then open AOT (developer workspace) in AX client.
Go to AOT > Service Groups > AifProject > right click and Deploy Service.
Go to AOT > Service Groups > AifProjWBS > right click and Deploy Service.





AX client configuration

The MS Project integration is designed to use the default client and Business Connector configuration and there is no option to specify a configuration file, so you can only connect to one AOS/AX system at the time.
If you need to connect to another AX environment (e.g. if you have a prod and test system), then you need to open AX client configuration utility (from Administrative tools).
For both configuration targets – AX client and Business connector:
Select the configuration for the other AX system and click Apply.
Note: You can have only one AX client and one MS Project instance open at the same time.



Set up parameters for Microsoft Project integration

Go to Project management and accounting > Setup > Project management and accounting parameters > General
Specify where to save the project files.

If you select “Local or network folder”:
Do not use _ (underscore) in the folder path/name.
Example: Do not use \\server\Project_Files - use \\server\Project Files or \\server\ProjectFiles
Use a network folder (UNC path) in multi user environment. Local is only for single machine test environment.





It is also possible to select to store the project files in SharePoint Collaboration workspace.
You can store Microsoft Project files in Microsoft SharePoint only if the associated collaboration workspace is using a project site template or team site template. You can change those settings in the Collaboration workspace settings form.

Be sure that all project users have access to the folder/workspace where the project files are stored.



Project categories



In order to be able to select Project categories in MS Project then the Project Category (Project management and accounting > Setup > Categories > Project categories) must be set up as Transaction type = Hour and Active in journals = enabled.



All Project categories specified on WBS lines must have this setup.



Some links to documentation and info:



TechNet doc:
https://technet.microsoft.com/en-us/.../dn528663.aspx



Project Management whitepapers:
http://blogs.msdn.com/b/axsupport/ar...t-project.aspx



Project Management demo on YouTube:
https://www.youtube.com/watch?v=XZrI...ature=youtu.be






Источник: http://blogs.msdn.com/b/axsupport/ar...irst-time.aspx
__________________
Расскажите о новых и интересных блогах по Microsoft Dynamics, напишите личное сообщение администратору.
 

Похожие темы
Тема Автор Раздел Ответов Посл. сообщение
emeadaxsupport: Get started with AX 2012 R3! Blog bot DAX Blogs 0 05.05.2014 09:11
atinkerersnotebook: Walkthrough & Tutorial Summary Blog bot DAX Blogs 1 09.09.2013 09:11
DAX: Official Dynamics AX 2012 R2 Content (update) - Where is it, and how can you find out about updates? Blog bot DAX Blogs 0 03.12.2012 11:11
emeadaxsupport: New Content for Microsoft Dynamics AX 2012 : October 2011 Blog bot DAX Blogs 0 27.10.2011 17:11
daxdilip: Whats New in Dynamics AX 2012 (A brief extract from the recently held Tech Conf.) Blog bot DAX Blogs 7 31.01.2011 12:35
Опции темы Поиск в этой теме
Поиск в этой теме:

Расширенный поиск
Опции просмотра

Ваши права в разделе
Вы не можете создавать новые темы
Вы не можете отвечать в темах
Вы не можете прикреплять вложения
Вы не можете редактировать свои сообщения

BB коды Вкл.
Смайлы Вкл.
[IMG] код Вкл.
HTML код Выкл.
Быстрый переход

Рейтинг@Mail.ru
Часовой пояс GMT +3, время: 11:56.
Powered by vBulletin® v3.8.5. Перевод: zCarot
Контактная информация, Реклама.